Plaza Deck/Garage – Threshold Summary Report 29 – 03.20.2026
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Tuesday March 17, Wednesday March 18, Thursday March 19, and Friday March 20, 2026....
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Tuesday March 17, Wednesday March 18, Thursday March 19, and Friday March 20, 2026....
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday March 09, Tuesday March 10, Thursday March 12, and Friday March 13, 2026....
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday March 02, Wednesday March 04, Thursday March 05, and Friday March 06, 2026....
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday February 23, Tuesday February 24, Thursday February 26, and Friday February 27, 2026....
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday February 16, Tuesday February 17, Wednesday February 18, and Thursday February 19, 2026. ...
Contract change is as follows: Scope: Per Change Order #9 1) Removal of approximately 8 courses of block in the parking garage at the supporting...
This is summary followup report from SKC's Milestone Phase 1 report
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday February 02, Tuesday February 03, Wednesday February 04, Thursday February 05, and Friday...
Biller Reinhart Engineering Group, Inc. (BillerReinhart) performed a site visit on Monday January 26, Wednesday January 28, and Thursday January 29, 2026. BillerReinhart and the...